I-5 bridge linking Washington and Oregon skyrockets to $14.4 billion as opening pushed to 2035
The I-5 bridge replacement cost doubles to $14.4 billion as governors prioritize core projects.
I-5 bridge costs double to $14.4 billion total. (Photo courtesy of (Oregon Department of Transportation)
(Photo courtesy of (Oregon Department of Transportation)
The plan to build a new Interstate 5 bridge between Washington and Oregon just got a reality check.
Washington Governor Bob Ferguson and Oregon Governor Tina Kotek announced that the estimated price tag has doubled, now reaching a staggering $14.4 billion. Along with the extra cost the timeline has shifted again with the new bridge not expected to open until 2035, two years later than the previous goal.
The project was originally expected to cost between $5 billion and $7.5 billion, but planners say inflation and the high cost of materials pushed the new range up to $13.5 billion to $15.2 billion. To keep the project moving, the governors are focusing on “core” parts of the bridge first, which includes the main spans and extending light rail into Vancouver. Governor Ferguson said at a conference the bridge will get built, stating, “We’re building this damn bridge. That’s happening.”
Concerns over costs and ‘political spin’
While several leaders are excited to finally see progress, others are worried about the significant budget. According to Oregon Capital Chronicle, Washington State Rep. Andrew Barkis, (R-Olympia) called the governors’ new focus on “core” projects a bit of “political spin.” Barkis noted that projects like this always seem to take too long and cost too much, warning that the states will likely have to come back to taxpayers for billions more in the future.
State Rep. John Ley, (R-Vancouver) also expressed doubt, saying that based on past experience, it would be shocking if the project doesn’t eventually require several billion more than what is currently pledged.
Critics like economist Joe Cortright warned that starting construction now is like signing up for “20 years of construction hell” and a $15 billion bill that won’t stop growing.
How the bridge will be funded
The two states currently have about $5.45 billion ready to go. The funding for this project comes from a mix of federal and state sources, including $2.1 billion in grants already awarded under the Biden administration.
Both Washington and Oregon have also pledged about $1 billion each to help cover the rising costs. To make up the rest, drivers will start paying tolls to cross the existing bridge in 2027, a move expected to bring in at least $1.2 billion for the program.
The next big step happens this September, when project leaders must show the federal government a solid plan for how they will pay for the rest of the work. If all the approvals go through in 2026, construction could finally start in 2028.
Follow Seattle Red on-air at 770 AM, on the Seattle Red app, and streaming audio and video on SeattleRed.com.





Comments
0 Comments