Sound Transit may cut Ballard light rail station as costs hit $22.6 billion
Dan Strauss urges Seattle residents to fight for the Ballard light rail station's future.
Sound Transit considers cutting the Ballard station. (Photo courtesy of Sound Transit)
(Photo courtesy of Sound Transit)
Seattle City Councilman Dan Strauss is calling on residents to fight for the future of the Ballard light rail station. At a community meeting Wednesday night, Strauss warned that the planned the Ballard Link Extension is in serious danger of being cut as Sound Transit struggles with budget failures.
Sound Transit is grappling with a $34.5 billion agency-wide funding shortfall projected through 2046, forcing the board to weigh cuts across the entire ST3 program. The problem, according to Strauss, is that most of the 16 members on the Sound Transit Board don’t live in Seattle. He says these “outsiders” don’t have a personal stake in making sure Ballard stays on the map.
Cost overruns and a 13-year delay threaten the Ballard Link Extension
The cost of the Ballard extension has skyrocketed. Originally estimated at $4.2 billion a decade ago, documents from earlier this month show the price tag has risen to as much as $22.6 billion, according to The Center Square.
Strauss admits that the agency has been overspending on “platinum standard” facilities that the city simply can’t afford. He noted that some underground stations are costing taxpayers $1 billion each because of “old ways of thinking” that added unnecessary features far beyond what building codes require.
To save the project, Strauss says the agency needs to stop aiming for platinum and start aiming for “gold.” His goal is simple, “I am looking for a train that runs,” he says.
Several residents at the meeting expressed anger over the potential cuts. In 2016, voters approved Sound Transit 3 (ST3), committing $27 billion in higher sales taxes, property taxes, and car registration fees specifically to pay for this expansion. Now, after paying those taxes for years, they are being told their station might end miles short of Ballard, potentially stopping at the Seattle Center or Smith Cove instead.
Even if the station is saved, relief won’t come anytime soon. Under the current 2026 schedule, the Ballard station isn’t expected to open until 2039. A final decision on the Ballard station is expected in May.
Follow Seattle Red on-air at 770 AM, on the Seattle Red app, and streaming audio and video on SeattleRed.com.






Comments
1 Comments
$34 BILLION over budget.
By getting rid of Ballard they cut $22 Billion. Add cutting West Seattle at $12+ Billion and their budget over runs is solved!!!
But come on, we KNOW they won't. They will put out an ST4 Levy for $100 BILLION with MORE unattainable goals and the DemoncRAT drones in Seattle will vote for it.